BVEM Bottom feed vibroflot system applied in offshore stone column constructionViews:72times
1. Project name: 200000 ton channel project in the middle zone of Caofeidian port area of Tangshan port (2021 year) Main equipment : bottom feed vibroflot, crawler crane, materials ship and excavator. Construction parameters : from - 9m underwater, the working depth of 15-17m, pile diameter is 1m, more than 3000 piles have been formed, total 25000 linear meters 2. Project name : Tiba Bay New Container Port Project in Timor Leste ( 2019-2020 year ) Main equipment : bottom feed vibroflot, ship frame( with automatic feeding system) and Loader. Construction parameters: Depth of sea water:15 meters Depth of pile:Maximum 26 meters Muximum SPT:70 blows Quantity of pile:more than 14,000 pcs Automatic pile positioning system(RTK system for sea area) 3. Project name: HongKong Immigration artificial island project of Hongkong- Zhu Hai-Macao Bridge (2014-2015 year) Main equipment : bottom feed vibroflot, ship frame,materials ship and excavator. Construction parameters: more than 46000 piles have been formed, total 1.1 million linear meters |